This decision concerns the analysis of the wholesale market for the unbundled access and the wholesale market for the bitstream access. The CRC concludes that Belgacom has significant market power on these markets and therefore imposes a series of obligations to fulfil on the operator.

Following an appeal lodged by Belgacom, the decision was partially annulled by the Brussels Court of Appeal on 3 December 2014.

On 18 December 2014, BIPT adopted a renewal decision rectifying the annulled decision.

Following a new appeal lodged by Belgacom, the renewal decision was annulled by the Brussels Court of Appeal on 3 December 2015.

 

Back to top